ECA Group has been awarded two contracts for the BARRACUDA programme

2373 500 342 image de synthese du sna barracuda article pleine colonne

These contracts consist in providing spare parts for the electric propulsion motor and the static converters of the first fourth submarines under construction.

This project entails for ECA Group producing the wholeness of the equipment within a 14 months period.

Then, the deliveries will be dispatched every two years staggered in four parts, and may be stored according to the needs of each submarine.